Friday, March 13, 2009

Flood recovery continues

It has been an interesting winter for the Northwest Railway Museum. Our first January flood (historically, most flooding occurs in November) has created a variety of challenges but also a few opportunities.

To recover quickly, a rail contractor is performing the track repairs. For the Museum, this means that the track being repaired will get new ballast and a surface, line and dress. While we all would have preferred to avoid flood damages, it is comforting to know that the track will be at least as good as it was prior to the flood event.

It is an interesting period of contrasts too. Consider these two photos taken just two months apart at Fir Street in downtown Snoqualmie. One shows track being rendered unusable and the other shows it being rendered useful.

Here at the Northwest Railway Museum we are grateful for the broad-based community support that is allowing timely repairs. Without public support, the museum would not have been able to begin the flood repairs. An event such as this reminds some of us that many arts and heritage organizations can be just one major disaster away from permanent closure.

Tuesday, March 10, 2009

Tamping track

So Spike, what makes rough track smooth again? A surface, line and dress. Huh?

A few short decades ago, gandy dancers did this work with lining bars, hand operated jacks and tamping bars or shovels. Today, workers (or more correctly, one worker) use a multifunction machine called a production tamper to level and line the track, then "tamp" (or compact) ballast under the ties to hold them in position. A production tamper uses lights, sensors and a servo circuit to detect deviations from profile (low spots in the track or lateral misalignment). Another function activates a jack to lift the track to the proper level and push it to one side or another until the sensors indicate that it is back in a straight line (or conforms to a predetermined curve). Confusing? Perhaps to most of us so instead check out these photos of a Jackson 6300 in action (followed by a ballast regulator to broom the extra ballast off of the track) and see the end result at the bottom. (Tip: if you click on the photo, you will be able to view a full screen version.)

























Sunday, March 8, 2009

Flood repairs begin

Damage surveys are complete, reports have been written, and funding applications have been filed. Resources to fully fund the repairs will take months to secure – or at least attempt to secure – but now it’s time to begin the repairs so they will be completed in time for April trains. RailWorks of Chehalis-Centralia was the low and successful bidder, and they began work this week. There were three bids with base prices that ranged between $59,000 and $140,000. Bids were based on unit costs and the actual cost will reflect the final quantity of materials and footage of track.

A large contractor such as RailWorks has a lot of resources to draw on in undertaking the flood repairs. Arriving on site this week was a veritable parade of specialized equipment, most of it new and all of it fully operational. And with it came a well-qualified and dedicated crew including the foreman Jim W., a Mt Si High graduate and former resident of Fall City. Some of the equipment is specialized for railroad work but other pieces are more common machines with hyrails, special railroad wheels that can been lowered or raised to operate on or off the track. Examples of the latter include a small excavator and a dump truck.

Repair work included in the scope of this project includes replacing about 700 tons of washed out ballast, surfacing over 2,000 feet of track, and adding rip rap to the inlet and outlet of a large culvert. Also as part of the project, nearly 100 cross ties are being replaced. Work is expected to take about 2 weeks. This contract will not address damage to electric gates, journal boxes, the Rainier gang car, or general debris clearance.

Thursday, February 26, 2009

Spacing out the ties

Railroad ties are ubiquitous and often taken for granted yet there is more to a tie than meets the eye. At the Northwest Railway Museum, a standard cross tie is 6 inches by 8 inches by 8 feet long and it is treated with either creosote or copper naphthanate. In well-drained ballast (the crushed rock the tie is placed in), it will last for 30 or more years. and over that time support millions of tons of trains.

Ties support the rails and distribute the weight of a passing train on the ballast. Ties also hold the track "in gauge," which is the distance between the two rails. For maximum effectiveness, ties must be evenly spaced. But when trains are braking or accelerating, or even just as the rails expand and contract in the heat and cold, there is a tendency for the track to "creep" and this causes ties to "creep" too. The end result is crooked alignment and uneven spacing. Once upon a time, badly misaligned ties were straightened by digging out the ballast from around the tie and moving it with a long steel bar -all by hand.

In the 1970s, some enterprising design engineers devised a hydraulic tie spacer. A diesel engine drives a hydraulic pump to pressurize a fluid - usually oil - to about 2,000 pounds per square inch. This pressurized fluid is used to force giant pistons back and forth. Those pistons are connected to a steel foot that can hook the end of a tie and move it in either direction. Of course the hydraulics are used to perform other functions too including propulsion.

The Northwest Railway Museum has a tie spacer that came from the British Columbia Railway but is similar to units once used in Washington by the BNSF and Union Pacific. Last fall, the tie spacer was rehabilitated in the Conservation and Restoration Center and is now used to help maintain the railway.