Saturday, March 29, 2014

Bridge repairs

So you think you can repair a bridge?  Well great, you start tomorrow!  Now if only it were that simple . . .

Damaged sections are obvious but
the method for replacement is not.
Most bridges are near water and at a minimum require a hydraulic permit before work can begin, and this usually adds conditions to a project.  Railway bridge work - by law - must be supervised by someone experienced in the maintenance and repair of railway bridges.  And any modifications must be reviewed by a qualified railway bridge engineer.  So even the damage caused by a tree striking a bridge triggers a variety of additional requirements besides just ordering new timber.

A tree striking a bridge?  Yes, that was the subject of a recent blog post. A very large tree struck and damaged formerly Northern Pacific's Bridge 35's trestle during a recent windstorm. Bridge inspectors allowed several trains to pass but stipulated that permanent repairs had to be undertaken right away. And as one of the largest objects in the Museum collection, how those repairs are performed is also critically important for collection care standards. So the Museum committed to completion prior to the start of the 2014 operating season using an experienced contractor and licensed engineer.

First of the timbers required to repair
Bridge 35 arrived and were moved to
the site using the Speedswing.
Step one: given the urgency of the bridge repair, the Northwest Railway Museum was able to secure an emergency hydraulic permit. Step two: pressure-treated railway bridge timbers were located in South Dakota (ironically, made from Douglas fir cut near Tacoma) and were ordered. Step three: a qualified contractor, foreman and engineer were identified and hired.  Step four: real work begins!

Stringers under the timber deck are
exposed during the pile cap replace-
ment.
To help control costs, some of the site preparation was performed by community work crews. They removed bolts and shovel railway ballast off the deck. In addition, Museum volunteers cleaned, chased threads, and primed the bolts to allow reuse. And the Museum agreed to supply the materials to avoid handling charges from the Contractor.

Bridge deck is supported
with blocking and a wide
flange beam.
Late in March 2014 Pivetta Brothers Construction began work on the bridge under the supervision of Muth Consulting Engineers.  Best practices including a silt fence were established to prevent any silt, dirt, rock or pieces of wood from getting in the river. Concrete ecology blocks and timber jacking pads were situated under the damaged section. Damaged deck and curb timbers were removed along the the stringers. Bracing and bolts were removed from the pile cap. Then blocking was used to support a wide flange beam that in turn was used to support the bridge deck. This allowed the damaged pile cap (the end was lightly crushed when the tree hit) to be removed and replaced.

Two new stringers were installed
above the new pile cap.
Two stringer sections each 28 feet long, 9 inches wide and 18 inches deep were damaged by the tree strike.  These were replaced with two new Douglas fir stingers of similar (slightly wider) dimension that were pressure treated with copper naphthenate preservative. The timbers had to be drilled for indexing pins, and for bolts to tie the stringers to the deck and ballast curb.

Total working time for the trestle repair was five days and was completed before the end of March; costs exceeded $25,000.  Ideally, this would have been the extent of bridge work for 2014.  However that was not to be and will be the subject of an upcoming blog post.


Damaged section is repaired!  New ties have been installed
and the track is about to receive new ballast.  The new and
existing ballast curb is shown on either side of the deck.


Tuesday, March 25, 2014

A bridge not far enough!

A recent wind storm has had a devastating impact on the Northwest Railway Museum's bridge 35.  A large cottonwood tree that measures more than five feet at the base has blown over and landed on the structure.  Estimates are that the tree weighs more than 12,000 pounds and the bridge was subjected to the entire force.

While the tree was intertwined with the bridge structure, damage appeared to be minor. Unfortunately, serious damage became obvious as soon as the tree was removed. Significant damage was sustained by the outer stringers, a pile cap, and some of the deck boards that support the ballast.

Bridge 35 brings the railroad into downtown North Bend and consists of a through-pin-connected Pratt truss and two segments of conventional wood trestle structure. The Pratt truss was first erected over the Yellowstone River in Montana in 1891, and moved to North Bend in 1924. However the damaged section is constructed of timber and dates from 1923.  The last major work on this section was performed in 1964.

A bridge inspection and cost estimates are driving the repairs.  The Museum blog will feature another post while repair work is underway.



Saturday, March 22, 2014

A signal indication

Winter weather often brings challenging driving conditions, and with that comes the inevitable opportunity for mishap. And so was the outcome of a recent winter driving incident at the Snoqualmie Parkway railway crossing.  The incident did not involve a train or engine, and there were no serious injuries.  However, the multiple vehicle accident resulted in the loss of a mast and signals in the center median when a deflected vehicle struck the mast, broke it off at the base, and the resulting impact with the local terrain damaged nearly every component.  Fortunately, no one was seriously injured, and the vehicle owner was appropriately insured.

The Northwest Railway Museum is responsible for five railroad crossing signal systems. With limited project work and just occasional component failures, the Museum only rarely purchases replacement parts.  So it came as quite a surprise to learn how much consolidation and change in the railroad signal industry has taken place in the last few years: now many signal components are supplied by Siemens Rail Automation, and nearly everything is made to order. So instead of purchasing parts "off the self," a new assembly was ordered.  About six weeks later, it arrived on a truck ready for installation.
The installation was completed in a few hours and the system was tested.  Costs totaled more than $6,000 and were fully reimbursed by the vehicle's insurance carrier.  Now the Snoqualmie Parkway signals are back in service and ready for the upcoming operating season!